Overview
- Document type and authority: A policy of the Government of Jammu & Kashmir (GoJK), prepared by the Jammu & Kashmir Energy Development Agency (JAKEDA), Science & Technology Department, dated 2017 on its cover.
- Background: Only about 15% of the State's hydro potential has been harnessed, mostly through medium and large projects; earlier hydel policies of 2003 and 2011 offered incentives, but there is huge space for improvement.
- Trigger for revision: The GoJK enhanced JAKEDA's mandate for hydel projects from 2 MW to 10 MW (order no 10-PDD of 2017 dated 11-01-2017), necessitating a new, more investor friendly policy.
- Energy context: The State, historically a net energy importer, faces serious imminent energy shortages as demand grows and power procurement prices rise.
- Target: Achieve 1000 MW installed capacity in the next 10 years, split between EPC (500 MW) and IPP (500 MW) modes.
- Strategic objectives: Energy security, economic benefits and social equity through mainstreaming small hydel energy.
- Policy goals: Increase small hydel deployment, meet increasing demand, introduce investment-friendly incentives, support private financing, integrate energy with social infrastructure in underdeveloped areas, build capacity and foster a domestic manufacturing base.